Projects performed and status by the South Orange Water Utility:

 Projects Status
 NJAW Pumping Station and Pipeline Complete 
 System Hydraulic Study Complete
Leak Detection Analysis Ongoing
 Hydrant Repair Study & Plan             Ongoing
 Well 17 Rehabilitation  Decommissioned
 Well 17 Carbon Filtration System Cancelled
 Stand Pipe Repair (Crest Drive) / Replacement Permit Issued by DEP
 Water Sphere Repair/Painting (Newstead) TBD
 Interconnection Upgrades NJAW Luddington - Complete, EOWC - Complete
 System Maintenance to Valves, Hydrants, etc. Ongoing
 Scotland Road Water Main Replacement Complete
 AMI Meter Replacement Project Meter-Tek 95% - AMI Implementation 
 Lead Line Identification and Replacement Project Ongoing
West End Road Main Replacement Complete