Project Summary
On February 10th the Township of South Orange Village awarded All State Technology the Peter S. Connor Memorial Pool improvements project. The project includes resurfacing the main pool, intermediate pool and baby pool along with replacing the main pool decking and repairing a leak under the main pool gutter.
Improvements
Resurfacing all three pools with a new Diamond Brite pool surfacing
Replacing all tiling in all three pools
Replacing all main drains with new VGB compliant covers for all three pool
Repairing a leak in the main pool
Removing and replacing the existing main pool concrete deck
Improving ADA access to the covered picnic area
Installing new bonding and grounding wire on all three pools
Fixing drainage issues on the pool grounds
Schedule: DUE to COVID-19 the project schedule has been delayed.
The project was awarded
| February 10th, 2020
|
Start of Construction | February 24th, 2020 |
Site work and demolition | February 24th - April 10th, 2020 |
Installation of new bonding and grounding wire
| April 13th -15th, 2020
|
Pour new concrete deck for main pool and ADA Access
| June 11th - 13th, 2020
|
Install drainage on site
| April 13th- 17th, 2020
|
Install new pool surfacing, tile, drain covers and repair pool leak
| June 15th- 20th, 2020 |
Final punch list and site work
| June 20th - 25th 2020 |
Completion of Project
| June 25th, 2020
|
Project Manager/Contact
Peter Travers, Director of Recreation and Cultural Affairs
973-378-7754 x2322