Peter S. Connor Memorial Pool Improvements

Project Summary

On February 10th the Township of South Orange Village awarded All State Technology the Peter S. Connor Memorial Pool improvements project. The project includes resurfacing the main pool, intermediate pool and baby pool along with replacing the main pool decking and repairing a leak under the main pool gutter. 

Improvements

Resurfacing all three pools with a new Diamond Brite pool surfacing

Replacing all tiling in all three pools

Replacing all main drains with new VGB compliant covers for all three pool

Repairing a leak in the main pool

Removing and replacing the existing main pool concrete deck

Improving ADA access to the covered picnic area

Installing new bonding and grounding wire on all three pools

Fixing drainage issues on the pool grounds

Schedule:  DUE to COVID-19 the project schedule has been delayed.

The project was awarded
February 10th, 2020
Start of ConstructionFebruary 24th, 2020
Site work and demolitionFebruary 24th - April 10th, 2020
Installation of new bonding and grounding wire
April 13th -15th, 2020
Pour new concrete deck for main pool and ADA Access
June 11th - 13th, 2020
Install drainage on site
April 13th- 17th, 2020
Install new pool surfacing, tile, drain covers and repair pool leak
June 15th- 20th, 2020
Final punch list and site work
June 20th - 25th 2020
Completion of Project
June 25th, 2020

Project Manager/Contact

Peter Travers, Director of Recreation and Cultural Affairs

973-378-7754 x2322